img(height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=2939831959404383&ev=PageView&noscript=1")

Contractor and sub contractor insolvency: What to look out for and action to take

Words:
Paul Cacchioli

Construction insolvencies are on the rise. What can architects do to spot and avert disaster?

Can you reduce the risk of contractor insolvency and site work grinding to a standstill?
Can you reduce the risk of contractor insolvency and site work grinding to a standstill? Credit: Istock

The number of insolvencies in construction is on the up according to figures from the government's Insolvency Service. In fact analysis by law firm Shakespeare Martineau shows that the construction industry accounted for 16% of administrations in 2022. The figures are a reminder of the impacts on architects.

There are short term concerns – making sure practices don’t have project financial liability if a contractor (whatever tier) goes bust and managing the work pipeline if contractor insolvencies stall projects. Longer term, these insolvencies don't help with the chronic and accelerating construction worker shortage; company insolvencies may make people move out of the sector. Forecasts of recession are not helping. So how can practices manage this?

Afloat in choppy waters

In addition to these supporting incentives, on 26 June 2020 the government also introduced the Corporate Insolvency and Governance Act 2020 (CIGA) in an attempt to protect businesses in financial distress as a result of the pandemic. There were some important permanent reforms from this. 

While employers and contractors will be buoyed by the investment and forecast recovery, they will need to tackle the dual constraints of the growing skills and materials shortages if they are to meet this rising demand

Permanent reforms consist of three strands. First is the restructuring plan, which gives a company in financial distress the opportunity to agree a restructuring arrangement with its creditors. Secondly, a moratorium is available, a ‘freeze’ which is intended to provide companies with a formal process to explore and develop a viable restructuring plan. Importantly, this also offers the company in question legal and enforcement protection. It is worth noting that, while the company remains under its own management during the moratorium (initially 20 business days but extendable by agreement or as ordered by a court), an insolvency practitioner is appointed to help protect creditors and provide some supervision. Finally, the statute seeks to limit the ability of a supplier to terminate the contract in the event that a company becomes insolvent.

Moreover, the government has also attempted through the Construction Playbook to reinforce the principle of prompt payment to all suppliers, and in turn their supply chain, to safeguard the delivery of public sector projects and programmes.

In support of this fundamental provision, public sector employers such as Network Rail have led the way by implementing other methods of relief for at risk businesses within their supply chains on a case-by-case basis. Such measures include immediate payment terms, advanced payments, increased frequency of payments, relaxation of relevant contractual terms and the payment of reasonably incurred additional costs arising as a direct result of Covid-19.

The walking dead?

While such support and protection provided by the government and enacted by public sector employers should be applauded, there is a danger that some measures have only delayed the inevitable. Are a number of these businesses unlikely to recover from the pandemic with low growth rates verging on recesssionary, and, have they in fact, become zombie companies?

Protective measures

It is important that businesses remain alert and monitor their supply chain to protect themselves from any failures within it. In terms of protective measures, it seems that employers and contractors alike are seeking appropriate guarantees, warranties and bonds throughout their supply chains. A greater level of financial due diligence and scrutiny is also being imposed throughout the market to validate the financial wellbeing of suppliers.

The construction industry accounted for 16% of administrations in 2022

Monitor for financial distress

Notwithstanding these protective measures, constant monitoring is vital. However, early signs of financial distress can be seen in a number of ways, for example: a high turnover of staff, general decrease in on-site labour, works slowing down or not achieving project timescales or milestones, poor quality workmanship and/or an increase in defects, and the removal of plant, equipment and/or materials from site.

Also, as a consequence of its financial hardship, certain actions by a company to improve its cash flow may be a cause for concern. These may include: requests from the contractor for changes to the payment mechanism, inflated applications for payment and/or unsubstantiated claims, complaints from sub-contractors regarding payment, a lack of response to correspondence, and late filing of statutory accounts and annual returns.

Any company seeing these warning signs, and a rise in the risk of insolvency, must act quickly to protect itself. It can adopt some simple ‘do’s and don’ts’ to help safeguard its position and avoid various pitfalls.

Safeguard: do’s and don’ts

Things to avoid without taking legal advice include: terminating, novating, or assigning contracts, appointing a new contractor to carry out relevant work, paying sub-contractors directly and making advance payments or paying for off-site materials.

Pre-emptive steps

There are pre-emptive steps that a company could adopt to prepare and ready itself. There are at least six such steps, for example, a company should ensure it has a complete set of contract documents (including warranties and guarantees) as these are often not conveniently stored and /or are incomplete. It should also establish a full list of the contractor’s management team, identify sub-contractors that are critical to the timely completion of the works and check whether collateral warranties are in place, and clarify its rights and obligations in the event of an insolvency, such as seeing if it has step-in rights.

Further moves would be to schedule and, if possible, safeguard any plant, equipment, and materials it has paid for, get the paperwork in place – instigate the full monitoring of progress and determine the scope and value of the work remaining (mark up drawings, take photos, and so on), and prepare a contingency plan in the event of the contractor’s insolvency (in the form of identifying other suitable suppliers, identifying critical supply chain members and materials, etc).

While it remains unclear how the construction sector will respond to the challenges of the current climate as the government support is eased, it is imperative that firms remain vigilant.

Paul Cacchioli is a chartered quantity surveyor and director of HKA Global. Additional analysis by Adrian Malleson, head of economic research at the RIBA

Latest

Terry Farrell exposes the philosophical aspects of postmodernism which embraced the complex reality of life, writes Owen Hopkins

Terry Farrell interprets the philosophy of postmodernism

AI’s effect on architecture, an ever-growing focus on sustainability and better ways of collaborating were among the key themes of the day, which explored the latest developments in Vectorworks’ software

AI’s effect on architecture, sustainability and collaboration were among the day’s key themes

Danish museum reveals architects using fungi, trees and other natural behaviours to create buildings that work with the environment rather than trying to tame it

Don’t try to beat nature; join it

Bring together a multidisciplinary team to create an outdoor commemoration space, bid for a pair of Sheffield city centre regeneration projects, submit a current sustainable project for an international prize - some of the latest architecture competitions and contracts from across the industry

Latest: Design a memorial to the late Queen

Sustainable design remains a priority in the race to supply homes to alleviate the housing crisis. Industry experts discuss some of the issues – and potential solutions

Sustainability is a priority in the race to supply homes