img(height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=2939831959404383&ev=PageView&noscript=1")

Mass timber construction joins the conservation sector

Words:
Jan-Carlos Kucharek

Sustainability credentials helped Feix & Merlin persuade the client that a mass timber insertion was the way to restore Walworth Town Hall

The ground floor cafe glulam structure before the addition of the CLT floor slab. The structural insertion took just three weeks.
The ground floor cafe glulam structure before the addition of the CLT floor slab. The structural insertion took just three weeks.

What Mass timber insertion
Where Walworth Town Hall, London


With mass timber construction making serious inroads for newbuild, it is used less often for conservation. But it is the centrepiece in the restoration of the grade II-listed Victorian Walworth Town Hall in Southwark, which was added to English Heritage’s At Risk register after being badly damaged by fire in 2013. Feix & Merlin convinced its client General Projects, which won the bid to restore the former council offices to commercial and community use in 2017, to use it – not least for its sustainability credentials.

Eight months into an 18-month construction programme, those mass timber elements have been craned into the former debating chamber, so the contractor can make the building watertight and proceed with internal works. Because the planners stipulated that the outside of the building must look as it did before the fire, explains senior architect Josh Piddock, Feix & Merlin worked closely with engineer HTS, which had experience of using mass timber in a conservation context.

  • The hybrid roof structure in position.
    1 of 2
    The hybrid roof structure in position.
  • Longer-run glulam beams connect to column heads with steel flitch plates. Interstitial beams use SHERPA connections.
    1 of 2
    Longer-run glulam beams connect to column heads with steel flitch plates. Interstitial beams use SHERPA connections.
12

Sitting in the centre of the plan, the almost square 156m² space now forms the social and circulation hub of the building. A new café and orientation space at ground level sits below the former council chamber, an expanded triple height co-working space reached directly from the refurbished Victorian Town Hall stair. Crowning the insertion, a new mass timber roof follows the original roof line.

Piddock says sensitivity to the original building drove the design. He adds that the timber has a materiality distinct from the original structure but the new glulam beams’ gentle arches make subtle reference to cambered arches above the original windows. It also led the firm to set out the structural columns and beams at ground level to follow the original wall lines, leading to an initially curious structural set-out. The 2.7m high, 280mm² glulam columns connect to the beams in different ways. Main spans are connected via steel flitch plates and countersunk bolt holes, while smaller arches spanning longer runs use SHERPA connections, whereby beams slide down and embed in the structure under their own weight. 200mm thick CLT floor slabs register into a 200mm by 50mm rebate cut out of beam edges, bringing the ground floor to soffit height to 3.6m. In a post-modern flourish, large, bare timber cornices are CNC cut, based on original cornice styles found nearby.

  • Section through the council chamber, now with mass timber insertion.
    1 of 2
    Section through the council chamber, now with mass timber insertion.
  • Worm’s eye view of the 3D model shows glulam and CLT elements of timber insertion.
    1 of 2
    Worm’s eye view of the 3D model shows glulam and CLT elements of timber insertion.
12

Engineered hybrid glulam and the steel roof structure came from a desire to minimise the thickness of structural elements, but the use of steel here ties in materially with the burnished steel mezzanine balustrade below. This hybrid arrangement reduced timber elements to 240mm square sections. Originally envisaged as a large rooflight, concerns about too much sunlight and glare in a workspace saw this replaced by an illuminated Barrasol ceiling, sub-divided into nine square sections by deep CLT beams lowering the roof height from 7.4m to 10.7m and creating a dramatic focus.

With a tight programme, the café and council chamber timber structure were pre-fabricated, delivered to site and erected in three weeks. Feix & Merlin is now working on its third-floor timber pavilion structure, whose erection should be complete by the start of December.

Latest

20 May 2025 from 9am to 11.30am

RIBAJ Spec: Architecture for Housing and Residential Development Webinar

Bid for a place on a port and harbour agreement, design the wind turbines of tomorrow, propose an installation for a public square in the Barbados capital - some of the latest architecture contracts and competitions from across the industry

Latest: Port design framework

After many years of driving along the A40 Westway to get to jobs, photographer Andrew Meredith began exploring the troubled history of a road that divides west London in two

Photographer Andrew Meredith captures the essence of a road that divides west London in two

The bold, angular looks of architect Adrian James’s home belie a low-impact timber-frame house that optimises solar gain, is zero carbon in use and aims to offset its embodied carbon within 30 years. What was the thinking behind the form?

Architect Adrian James’s unusual-looking home is zero carbon in use and aims to offset its embodied carbon within 30 years

Hawkins\Brown and RPP Architects conjure an environment that's both welcoming and revealing within a bright red exposed steel frame, giving students a great place to hang out

Hawkins\Brown and RPP Architects conjure a welcoming space within an exposed steel frame

1
12
12